ANSI Process Pump Selection Guide

Use this guide to prepare the technical information needed for an ANSI/ASME B73.1 process-pump enquiry. It is a buyer checklist, not a substitute for a reviewed performance curve, material evaluation or installation calculation.

Quick start

The Six Decisions in a Pump Selection

Define the duty point, describe the liquid, verify the suction system, choose the pump-family route, review materials and seals, then request the correct technical documents.

1. Define the Duty Point

Hydraulic duty

  • Minimum, normal and maximum flow
  • Total dynamic head, discharge pressure or system curve
  • Continuous, intermittent or standby operation
  • Expected control method and parallel operation

Operating envelope

  • Normal and upset conditions
  • Startup and shutdown frequency
  • Required margin and project specification
  • Available motor speed and electrical supply

A series maximum is not a model guarantee. The selected size, impeller, speed, material and seal determine the applicable limit.

2. Describe the Liquid Completely

InputWhy it matters
Composition and concentrationSupports material and seal review; trade names alone may be incomplete
Minimum and maximum temperatureAffects vapor pressure, viscosity, materials, seals and clearances
Density and viscosityAffects power, curve correction and pump-family suitability
Solids, particle size and concentrationAffects impeller, clearances, seal environment and wear review
Toxicity, flammability or crystallizationAffects containment, seal plan, cleaning and operating controls

3. Verify the Suction System

Provide the source vessel, minimum and maximum liquid level, pump elevation, suction-pipe diameter and length, fittings, strainers, valves, vapor conditions and operating pressure. This information supports NPSH and priming review.

Flooded suction

Confirm the available static head and the losses between the source and pump inlet. A positive liquid level does not remove the need for an NPSH check.

Suction lift or intermittent source

Provide lift, line volume, air-leak risk, priming method and liquid-level variation. A self-priming label alone does not confirm a workable installation.

4. Choose the Pump-Family Route

Duty patternStarting routeReview before selection
General industrial or chemical process dutyG196 Series or D Mark III SeriesSize, impeller, material, seal and applicable curve
Operating point persistently below a standard pump’s suitable rangeLow-flow model within the applicable seriesBEP position, minimum flow, recirculation and curve
Source below pump elevation or repeated priming needSelf-priming reviewSuction layout, lift, air leakage, priming liquid and vapor conditions
Paper stock or heavy-duty high-volume serviceG 3175 / 3180 / 3185 reviewStock properties, solids, size, materials and verified hydraulic data

5. Review Materials, Seal and Construction

Material selection must identify the wetted component, exact material grade and full service conditions. Seal review should include liquid lubricity, solids, vapor behavior, temperature, pressure, emissions requirements, flush availability and maintenance practice.

Material questions

  • Which components are wetted?
  • What concentration and temperature range applies?
  • Are impurities, cleaning fluids or upset conditions present?
  • What corrosion or wear history exists?

Seal questions

  • Mechanical seal or packing requirement
  • Seal chamber and flush environment
  • Solids, crystallization or dry-running risk
  • Leakage, containment and maintenance requirements

6. Request the Right Technical Documents

DocumentMinimum information to request itHow to use it
Reviewed performance curveModel, size, speed, impeller and duty pointCheck operating point, efficiency region, power and NPSH data
General arrangement drawingModel, size, configuration and drawing purposeCheck installation envelope, nozzles, base and interfaces
Parts list or exploded viewSeries, size, nameplate, revision and requested itemIdentify the correct component before quotation
IOM or technical manualApplicable model, version and languageSupport installation, operation and maintenance planning
Order data sheetConfirmed quotation or order configurationRecord the approved technical supply scope

Total Cost of Ownership Review

Do not compare pumps on purchase price alone. Include installation changes, expected operating point, energy use, seal and bearing environment, planned maintenance, spare-parts strategy, downtime exposure and document/support requirements.

Installation

Base, piping, alignment, utilities, controls and commissioning effort.

Operation

Energy, operating hours, control method and time spent away from the preferred region.

Maintenance

Seal, bearing and wear-part access, spares, inspection intervals and downtime risk.

Selection Guide FAQ

Can I select a pump from flow and head alone?

No. Flow and head define the hydraulic target, but liquid properties, suction conditions, materials, seals, operating range and project requirements can change the selection.

When should I review a low-flow pump?

Review a low-flow route when the required operating point would keep a standard pump too far left of its preferred operating region. The decision must be checked on the applicable curve.

When is a self-priming pump worth reviewing?

It may be relevant when the pump must lift liquid from below its elevation or when the suction source is repeatedly drained. The complete suction layout remains essential.

What does a reviewed performance curve confirm?

It ties the proposed size, speed and impeller to the duty point and shows the information needed to assess operating region, power and suction requirements.

What should I upload with an existing-pump enquiry?

Upload a clear nameplate, overall pump photos, existing drawing or datasheet, and close-up photos of the required part or problem area.

Ready for a Reviewed Selection?

Use the RFQ form to send the duty, liquid and project data. Add a nameplate or drawing when the request concerns an existing pump.

Send Your Pump RFQ

The technical review uses, where available: the duty point and operating envelope, liquid properties, suction conditions, material and seal preferences and the project requirements covered in this guide. For a replacement, add the existing pump identity — nameplate, model, size and drawings where available.

Open “Add technical details” to fill in what you know, and mark anything uncertain as unknown — a marked gap is reviewable, a silent one is not.

Pump RFQ

Replied by the technical team with the reviewed selection route and quotation scope.

Contact Us